Project Description

Construct WAFERS Training Facility, AAFB Guam – Completed 2017 

Prime Contractor – Tikigaq Construction, LLC – June 2017 – October 2017 

Procurement and installation of new cable, terminations, connectors, grounding equipment and miscellaneous items to connect the existing 150kva transformer to the power station enclosure, approx. 275’.

Procurement and installation of new cable, conduit, terminations, connectors, ground wire and miscellaneous items to connect the power station enclosure to the 200 amp and 60 amp disconnect switches. 
Procurement and installation of new cable, conduit, terminations, ground wire and miscellaneous items to connect the 200 amp and 60 amp disconnect switches to the motor starters and water pumps.
Procurement and installation of the new AMI KWH Meter enclosures, brackets and fasteners.
Electrical testing and commissioning support 

Status: Completed
Date Completed: October 2017