Project Description

Initial Set-Up and Installation of a 2MW Diesel Power Facility, Pohnpei – Completed 2014

Prime Contractor – VITAL Energy – October 2013 – September 2014  

Performed installation of High Voltage electrical cable, transformers, generators, control panels and miscellaneous electrical equipment for a 2 Mega-watt diesel generation facility on the island of Pohnpei. Performed the initial start-up, commissioning and testing of the facility. Trained all incoming operational staff prior to facility turnover. 


Status: Completed
Date Completed:  September 2014

Initial Set-Up and Installation of a 2MW Diesel Power Facility, Pohnpei